What's Going Up Behind the Naples Pier Fence Is Built for the Next Storm

November 5, 2026

The Naples Pier will be closed for the whole 2026–27 season. The City of Naples says the rebuild is on schedule to reopen in July 2027. What you can see from the Broad Avenue South beach end this winter is the heaviest part of the new pier: concrete pilings, concrete caps and the base for the midpoint pavilion. That order is deliberate. The engineers put their effort into the parts most likely to still be standing after a major hurricane. The parts that are easier to replace, like the wood decking, the shade structures and the food service, come later.

Ian Was the Latest in a Long Line of Storms

The pier has stood at the end of 12th Avenue South since 1888. According to the City's rebuild project page, it was rebuilt after storms in 1910, 1926, 1944 and 1960. A major renovation in 2015 was followed two years later by damage from Hurricane Irma, and five years after that Hurricane Ian hit.

Ian came ashore near Cayo Costa on September 28, 2022, as a Category 4 storm, about 104 miles from Naples. Even at that distance, about 140 feet of the pier, including the end shelter and more than 30 pilings, ended up on the Gulf floor. Waves gutted the concession area, the midpoint shelter and the storage rooms. City engineers found the structural components were compromised and decided to replace the whole pier instead of repairing it.

That history explains the design. A pier that has been rebuilt every few decades was redesigned with the assumption that the next storm will come.

What All That Concrete Is For

The new pier keeps the familiar shape. Naples Press reported that it will stay 1,000 feet long and 12 feet wide. What changed is mostly below the deck.

Element Previous pier Rebuilt pier
Pile size 14 inches square 18 inches square, a 65 percent increase
Pile length Shorter than any of the new piles 70, 85 and 100 feet
Height above water Baseline 3 feet higher
Poured concrete Baseline Nearly three times as much
Pile layout More piles, closer together Fewer piles, spaced farther apart
Midpoint shade Baseline About three times as much

These changes depend on each other. According to the City, the larger and longer piles added enough capacity to raise the deck 3 feet. The extra concrete improves the odds that the concrete part of the pier gets through a severe hurricane. The team also cut the number of piles and spaced them farther apart to reduce effects on the shoreline and erosion.

Turrell, Hall & Associates led the architectural and engineering design with MHK Architecture, and that team is now doing the construction engineering and inspection. The contractor is Shoreline Foundation Inc., which won the construction contract on October 2, 2024, for $23.5 million. Gulfshore Business put the full project at $26.3 million.

The Order of Work Visible From the Sand

Construction started January 6, 2026, the day after a public groundbreaking at the pier. Since then the work has gone in a set order:

  1. April 13, 2026. Demolition of the old pier was completed.
  2. May 5, 2026. Divers began a month of clearing debris from the seabed, including pilings buried since the 1990s, so the new piles could go in safely.
  3. June 17, 2026. Crews began building a temporary trestle along the south side so work could continue when the offshore barges had to take shelter from weather.
  4. June 26, 2026. The first concrete pour for the bents, the rows of pilings capped by crossbeams. The whole project needs about 602 cubic yards of concrete.
  5. September 18, 2026. The pour for the midpoint pavilion site took the project past half of the total concrete.
  6. October 7, 2026. The last of the 193 reinforced-concrete pilings was driven.
  7. October 22, 2026. Work began on the midpoint pavilion. It will have pressure-treated pine columns covered in one-inch Ipe wood.

The City credits a calm summer for keeping the work on pace. It also lists electrical work, bathroom and storage renovations and foundation improvements as under way.

Next, Shoreline Foundation expects to finish all structural work by early 2027. After that, crews install the Ipe decking and structures. Ipe, pronounced "ee-pay," is a tropical hardwood known for resisting rot. About two-thirds of the decking had already been delivered by late July, and it is waiting until the last of the concrete is poured. That means the bare concrete structure is what you'll see on walks this winter. By the time the decking goes down in 2027, most of it will be hidden.

Why the Concession Won't Come Back Out Over the Water

The old pier had a permanent concession at the midpoint, and many people remember it as part of a pier visit. It won't return in that form. The City says state and federal rules prohibit rebuilding the former mid-pier concession.

City Council looked at several options. It chose portable food and beverage carts at the midpoint pavilion, an approach the City says serves visitors while respecting nearby residents and businesses. Council also approved a small Naples Police and Beach Patrol substation on the pier. The landside design was presented to Council on March 4, 2026. According to Gulfshore Business, the entry area includes public restrooms along with the patrol office.

The carts fit the same logic as the concrete. The heavy, permanent parts of the new pier are built to stay. Food service is designed to roll on and off, and the pavilion gets three times the shade of the old shelter.

The Old Pier Is Now a Reef 10 Miles Out

The old pier wasn't hauled to a landfill. WINK News reported that on April 24, 2026, the City, Shoreline Foundation and Turrell, Hall & Associates placed 59 concrete pilings from the old pier at the Wasmer Reef site, about 10 miles offshore of Gordon Pass. In all, more than 300 tons of demolished pier concrete went into the reef.

It is the eighth reef built within the Wasmer site, permitted by the U.S. Army Corps of Engineers. Wasmer Reef started in 2015 as a multi-agency project funded by BP oil spill grants and private donations. WINK reported that it now supports corals, aquatic vegetation, invertebrates, bivalves and tunicates, which give young and mature fish shelter and food. Divers checked the site before and after the drop. Old pilings that didn't go to the reef went to a recycling facility to be crushed into aggregate for road construction.

Collier County's Coastal Zone Management Department runs the county artificial reef program and coordinates monitoring and maintenance. The County describes its reefs as supporting recreational and charter fishing and diving. For anyone in Naples with a boat, that puts a piece of the old pier within reach this season, a run out past Gordon Pass.

Getting to the Beach Around the Fence This Season

For about the 18 months of the project, the pier is closed. So are its stairs, restrooms and showers, and 12th Avenue South west of Gulf Shore Boulevard South. Here is how the area works until July 2027:

  • Beach access: The City has set up pedestrian bypasses at the Broad Avenue South and 13th Avenue South beach ends. Both stay open for the whole project, and both have restrooms.
  • Parking: Only the western third of the pier lot at 12th Avenue South and Gulf Shore Boulevard South is open to the public. The eastern two-thirds is a construction zone. Spaces in City beach lots need a beach parking permit or a pay-by-space payment.
  • Watching progress: The City's beach information page links to a 24-hour live video of the pier, so you can check on the pavilion work from home.
  • Fishing nearby: The pier itself is closed to fishing during construction. The City's dock rules also prohibit fishing from the municipal docks at Crayton Cove.

The City's project page adds new dated milestones as they happen, and it is the most reliable place to follow the rebuild between now and July.

If you're watching the pier come back and thinking about which stretch of beach you'd like to live near, Kyle Suhr knows the Naples beach ends and the streets that lead to them. Kyle R. Suhr is glad to talk through how the rebuild affects the blocks around 12th Avenue South. Discover Your Gulf Coast Lifestyle — Contact Kyle.

STAY UP-TO-DATE ON THE LATEST REAL ESTATE TRENDS

RECENT BLOG POSTS

Work With Me

I plan to bring my success to the local real estate industry to every client and beloved neighborhood. My expertise as a creative marketing liaison aligns traditional, digital, and social communications to offer strategic, creative counsel that meets client objectives while keeping them at the forefront of an authentic audience.